According to a report by Livemint, India’s defence manufacturing sector is facing renewed scrutiny as Hindustan Aeronautics Limited (HAL) comes under mounting pressure over delays in delivering TEJAS MK-1A fighter aircraft to the Indian Air Force (IAF).

The issue has attracted significant attention following criticism from a former IAF chief, who raised concerns over the slow pace of aircraft integration and production at a time when the Air Force is struggling with a declining fighter squadron strength.

The TEJAS MK-1A programme is a critical component of the IAF’s modernisation strategy and was originally intended to replace the ageing MiG-21 fleet through a phased induction process. Under the initial plan, newly manufactured TEJAS squadrons were expected to enter service as existing MiG-21 units were progressively retired.

However, aircraft deliveries have fallen considerably behind the original schedule. With the MiG-21 fleet being phased out faster than replacement fighters are being inducted, concerns have intensified over the impact on the IAF’s operational strength and overall combat readiness.
Engine Shortages and Supply Chain Bottlenecks
Although HAL has faced much of the criticism surrounding the delayed deliveries, government officials have acknowledged that the underlying challenges extend beyond domestic manufacturing facilities. The situation has exposed broader vulnerabilities in India’s aerospace supply chain, particularly its dependence on imported critical components.

A major constraint has been the delayed supply of GE F404-IN20 engines from the United States, which serve as the primary propulsion system for the TEJAS MK-1A. Described as the “heart of this entire aircraft”, the engine shortage has directly affected production schedules and the timely completion of aircraft.

To minimise the impact, HAL adopted an interim manufacturing strategy by completing aircraft structures and keeping them ready for final assembly until the engines became available. The approach was intended to accelerate production and enable quicker aircraft integration once engine deliveries resumed.

However, this arrangement has not produced the anticipated results. In addition to engine shortages, disruptions affecting other imported aerospace components have created further constraints across different stages of the manufacturing and assembly process.

The situation highlights a broader challenge confronting India’s defence industrial ecosystem. While the country has demonstrated considerable capabilities in developing sophisticated military aviation platforms, establishing reliable supply networks and scaling up production to meet large contractual requirements remain significant obstacles.
Government Reviews HAL’s Production Efficiency
Senior defence officials have also acknowledged that overseas supply disruptions alone cannot explain the delays. The government is examining whether defence public sector undertakings (DPSUs), particularly HAL, have sufficient internal production management capabilities, manufacturing efficiency and assembly-line capacity to meet demanding contractual schedules.

As part of its efforts to address these shortcomings, the government has introduced corrective measures aimed at improving accountability, strengthening supply-chain resilience and ensuring greater discipline in defence manufacturing programmes.

Defence public sector undertakings have been directed to undertake comprehensive supply-chain assessments within three months of receiving orders for defence platforms. These reviews are intended to identify potential vulnerabilities at an early stage, diversify procurement sources and reduce the risk of production delays caused by shortages of individual components.

The government has also strengthened the link between project execution and organisational performance assessments. Beginning this year, timely delivery will carry 10 marks in the performance evaluation framework for defence public sector undertakings, placing greater emphasis on meeting contractual commitments and delivery deadlines.
Implications for India’s Indigenous Fighter Programme
The TEJAS MK-1A programme remains central to the IAF’s efforts to modernise its combat fleet and address the growing gap between authorised and available fighter squadron strength.

However, the prolonged delivery delays have highlighted the risks associated with dependence on foreign suppliers for critical aircraft systems, particularly engines and other specialised aerospace components.

The situation has also renewed discussions about the distinction between indigenous technology development and large-scale industrial production. Developing an advanced combat aircraft is a significant technological achievement, but ensuring consistent manufacturing output, reliable component availability and timely delivery is equally important.

For India, resolving these challenges will be essential not only for the successful execution of the TEJAS MK-1A programme but also for future indigenous aerospace initiatives, including the TEJAS MK-2 and Advanced Medium Combat Aircraft (AMCA).

Ultimately, the programme’s progress will serve as an important indicator of India’s ability to transform its growing aerospace engineering capabilities into a dependable, competitive and scalable domestic defence manufacturing ecosystem.